March 2022 Exxel Pacific Update

February was another busy month. While the city-wide concrete strike continued, the team was able to divide-up the remaining concrete work into smaller pours allowing work to continue in these

Share
February 2022 Exxel Pacific Update

The concrete strike continued-on through the month of January, but great progress continued on the project. Inside the building, the Exxel team applied finish paint colors, rolled-out carpet, and installed

Share
January 2022 Exxel Pacific Update

December was a busy month, despite the holidays, snow days, and on-going King County concrete strike. Metal siding and roofing finished up on the outside of the building and install

Share
September 2021 Exxel Pacific Update

A lot of progress was made in the month of August at the Upper School as the New Building took big steps towards getting sealed-up. Installation began on windows, roofing

Share
August 2021 Exxel Pacific Update

Lots of activity happened at the Upper School this summer. All of the major structural wood framing wrapped up at the end of the month. Utility work in the roundabout

Share
???????????????????????????????????????????????????????????????????????????????????????????????

June was a busy month at the Bush Upper School project site. The generator between Wissner and Gracemont was pulled while extensive site utility work took place and is on-going.