April 2021 Exxel Pacific Update

The end of March brought another major milestone for the New Upper School Building – the basement level slab-on-grade was poured. The first half of April will focus on shoring

Share
Salmon Safe Progress:

Our commitment to Salmon Safe is an important part of the construction of the New Upper School Building. In following the guidelines for Salmon Safe, our general contractors Exxel Pacific

Share
March Update from Exxel Pacific

February was an exciting month for the New Upper School Building! Mother Nature threw us a few curve balls with snow and freezing temperatures one week and sunny skies the